Full Project – CAUSES AND EFFECTS OF DESIGN VARIATION IN ROAD CONSTRUCTION PROJECTS
Click here to Get this Complete Project Chapter 1-5
ABSTRACT
Variation is one of the most severe problems in the construction industry. This variation occurs in every construction project and the magnitude of these variations varies considerably from project to project. As such, the client had to spend more than what was initially estimated in most cases, sometimes, disputes and unnecessary delays occur due to variations. This study focused to investigate causes and effects of design variation in road construction project in Akwa Ibom State. The objectives were to examine the causes of design variation, to investigate the effects of design variation in road construction projects and examine measures to minimizing its occurrence. Relevant literature review on causes and effects of design variation in road construction projects were carried out and an elaborate field survey was undertaken to verify the objectives of this study. A total of 62 questionnaires were collected against 68 questionnaires distributed among professionals in the construction industry, representing 91% response rate. The data collected through a structured questionnaire administered to the professionals were analysed using simple random sampling technique. The results revealed that change in client’s opinions was the most predominant cause of variation. Others are consultant and contractors’ factors were also seen as the severe causes. The results also revealed that the most common effects of design variation on construction projects were increase in project cost, delays in completion and disputes among stakeholders. The study pointed early interaction between the design team and the client to ensure that client’s requirements are clarified and communicated effectively into the design to reduce variations. The study recommends team work spirit amongst stakeholders involved in the project and respect to original design by the client as the key ingredients for a successful project delivery.
CHAPTER ONE
INTRODUCTION
1.1 Background of the Study
The complexity of the construction industry due to different stakeholders’ involvement makes it differ from other industries. This complexity leads to unwanted situations like variations with their associated effects. And presently, it is almost becoming a rare thing for a construction project not to have variation. Most contracts these days must make provisions for possible variations given the nature of road construction project (Finsen et al., 1999). (Uff, 2005) further pointed out that a clause permitting variation of works is an essential feature of any construction contract because without it the contractor is not bound to execute additional work or to make omissions or changes. In line with these, the nature and approach to the conception, planning and subsequent actualization of construction projects are dynamic, complex, sophisticated and capital intensive in recent times. In consequence, these projects are subjected to adequate appraisals by the sponsors on the basis of political, social, projects relatives’ benefits, externalities, etcetera, with a view of ascertaining the values of money (Onwusoye, 2005). The certification for the realization of this objection through various techniques and other implied factors by the potential owner of the projects leads to the eventual take off of a construction project. Therefore, design variation need to be critically addressed as this continue to be a frequent problem that gets worse often in construction project. Though of recent, it is a common phenomenon for design variation to occur on construction project. But under normal circumstance, it is possible for a complex set of drawings and specification to be available for preparation of fully described and accurate bill of quantities for tendering purposes. These would deplete further charges as a result of design changes during the construction stage.
According to the J.C.T. 80, design variation in road construction refers to a change in the works initiated by the engineers, consultants, employer or other factors as the case may be which involves the alteration of any kind or standard of materials to be used in the work. A design change is regarded as any change in the design or construction of a project after the contract is awarded and signed, and such changes are related not only to matters in accordance with the provision of the contract but also changes to the work conditions. Akinsola et al (1997) also noted that these changes as any additions, omission or adjustment to the contract price or contract time, and it occurs regularly on construction projects. Park (2002) defined design variation as a change to the work state, processes or methods that differ from the original construction plan or specification and usually resulted from different in work quality and condition, scope changes or uncertainties that make construction dynamic and unstable. Affirmed that design variations are inevitable on major construction projects particularly on road construction where the project is complex, the ground conditions variables or the employer desire to incorporate the latest technology into the project. And the more design changes on a project, the greater effect which become time consuming and costly in construction projects (Mohamed, 2001). It is therefore of greater concern regarding the adverse effects of the design changes in both public and private construction in Akwa Ibom State.
According to Arian and Pheng (2005), design variation on road construction project resulted into a substantial increment in amount of funding budgeted for the work, hence caused the inability to complete and handover the work as agreed initially at the commencement of the work. As a result of this, it is extremely noticeable that time and cost overrun occurs due to variation in many construction projects especially road construction. Similarly, variation order which contains a set of instructions that allows changes or modifications to be made to as earlier agreement in terms of volume or nature of task to be carried out, (O’Brien, 1998). These changes are however occur after the award of the initial contract or after work might have commenced at the construction sites. The changes may be due to various reasons such as the modification of original design and scope, schedule, costs and methods.
Variation from the original project design is seen as the major causes of project failure, though project monitoring and control could cause corrective actions to bring deviation during construction but failed to take cognizance of identifying and analyzing the root cause of such variation (Ubani, Nwanchukwu and Nwukonkwo, 2010). The performance objectives defect due to variation of many completed and ongoing road projects resulted in employer’s dissatisfaction, project time extension and cost overrun, low quality and substandard outputs, project conflicting between the contractors and employers arising from variation in contract sum. And the unusual thing about it is the extent of such differences as well as the frequency occurrence. The causes and cost implication of variation needs to be assessed and analysed at the onset of the project, and it is on this background that the study was carried out.
1.2 Statement of the Problem
All road construction projects undergo various degrees of design variations throughout the project life cycle. Changes in construction projects are inevitable particularly when the actual work commences to correct or modify original design or scope of work (Alnuaimi et al., 2010). The research study by Naoum (1997) highlighted the lack of time and effective communication, lack of integration, uncertainty, a changing environment and increasing project complexity as the drivers of design changes.
According to a study by Ogunlana, Promkuntong and Jearkjirm (2000), construction owners are the major causes of design variations due to changing plans in line with the changing economic climate to meet customer demands or for making marketing reasons. Design variation need to be constantly monitored to avoid escalation (Olawale and Sun, 2010).
Get the Complete Project
This is a premium project material and the complete research project plus questionnaires and references can be gotten at an affordable rate of N3,000 for Nigerian clients and $8 for International clients.
Click here to Get this Complete Project Chapter 1-5
You can also check other Research Project here:
- Accounting Research Project
- Adult Education
- Agricultural Science
- Banking & Finance
- Biblical Theology & CRS
- Biblical Theology and CRS
- Biology Education
- Business Administration
- Computer Engineering Project
- Computer Science 2
- Criminology Research Project
- Early Childhood Education
- Economic Education
- Education Research Project
- Educational Administration and Planning Research Project
- English
- English Education
- Entrepreneurship
- Environmental Sciences Research Project
- Guidance and Counselling Research Project
- History Education
- Human Kinetics and Health Education
- Management
- Maritime and Transportation
- Marketing
- Marketing Research Project 2
- Mass Communication
- Mathematics Education
- Medical Biochemistry Project
- Organizational Behaviour
- Other Projects
- Political Science
- Psychology
- Public Administration
- Public Health Research Project
- More Research Project
- Transportation Management
- Nursing
Need a Project Writer for a Different Topic
- MSC PROJECT WRITING SERVICES
- MBA RESEARCH PROJECT WRITING SERVICES
- Research Project Writing Services in Lagos Nigeria (Professional Writers) -Law, MSc, MBA,PhD, Dissertations, Thesis, Assignment, Speech
- Masters Research Project Writer in Lagos Nigeria
- MBA Research Project Writer in Lagos Nigeria
- LOOKING FOR A WRITING SERVICES FOR AN URGENT ASSIGNMENTS OR PROJECT WORK
- PROFESSIONAL WRITING SERVICES IN LAGOS NIGERIA (TERM PAPER, SPEECH WRITING, ASSIGNMENT, THESES, DISSERTATIONS, RESEARCH PROPOSAL, PROJECT WRITING SERVICES etc)
- BUSINESS ADMINISTRATION RESEARCH PROJECT WRITER IN LAGOS NIGERIA
- CONSULT A RESEARCH PROJECT WRITER IN LAGOS NIGERIA (PH.D, MBA, MSC, M.ED, BSC)
- MANAGEMENT RESEARCH PROJECT WRITER IN LAGOS NIGERIA
- Education Research Project Writer in Lagos Nigeria
- Environmental Sciences Research Project Writer in Lagos Nigeria
- Guidance and Counselling Research Project Writer in Lagos Nigeria
- Human Kinetics and Health Education Project Writer in Lagos Nigeria
- Early Childhood Education Research Project Writer in Lagos Nigeria
- Christian Religious Studies(CRS) Research Project Writer in Lagos Nigeria
- Educational Administration and Planning Research Project Writer in Lagos Nigeria
- Political Science Research Project Writer in Lagos Nigeria
- Accounting Research Project Writer in Lagos Nigeria
- Economics Research Project Writer in Lagos Nigeria
- Management Research Project Writer in Lagos Nigeria
- Marketing Research Project Writer in Lagos Nigeria
- Public Administration Research Project Writer in Lagos Nigeria
- MBA Research Project Analysts
- In Need of MBA Research Project Writer in Nigeria
- MBA Dissertation Research Project Writer
- MBA Project writer
- EDUCATION DEPARTMENT PROJECT WRITING SERVICES
- BACHELOR OF SCIENCE (BSC) DEGREE PROJECT WRITING SERVICES(B.ED,B.A,B.SC)
- MASTER OF BUSINESS ADMINISTRATION (MBA) RESEARCH PROJECT WRITING SERVICES
- MASTER OF SCIENCE (MSC) RESEARCH PROJECT WRITING SERVICES
- POST GRADUATE RESEARCH PROJECT WRITER
- POST GRADUATE DIPLOMA (PGD) RESEARCH PROJECT WRITER
- MASTER RESEARCH PROJECT WRITER
- MASTER DEGREE RESEARCH PROJECT WRITING SERVICES
- POSTGRADUATE RESEARCH PROJECT WRITING SERVICES
- MASTERS RESEARCH PROJECT WRITING SERVICES
- RESEARCH PROJECT WRITER
- EXPERT IN RESEARCH PROJECT/THESIS/DISSERTATION WRITING SERVICES IN LAGOS NIGERIA
- HIRE A PROFESSIONAL BSC/HND RESEARCH PROJECT WRITER
- HIRE A PROFESSIONAL MBA/MSC RESEARCH PROJECT WRITER
- HIRE A PROFESSIONAL THESIS WRITER IN LAGOS NIGERIA
- SC/M.SC/MBA/PGD RESEARCH PROJECT WRITER IN LAGOS NIGERIA
- Master Degree Research Project Specialist/Writer in Lagos, Nigeria
- Hire A Research Project Writer in Lagos Nigeria
- Research Project Specialist in Lagos, Nigeria
Full Project – CAUSES AND EFFECTS OF DESIGN VARIATION IN ROAD CONSTRUCTION PROJECTS